8MW Steam Biomass Boiler Plant in Olaine City

Client:

Kanga Board Co Ltd.

Construction of the biomass fired (woodchips, sawdust) steam plant in Olaine, Latvia is now well underway.


We have started the deliveries of the technological equipment to the plant. Construction and installation phases will follow.


The project is designed to supply 10t/h of steam (16bar, 204C) to the new woodworking factory (Kanga Board Co Ltd.).


A successful realisation of the project will lead to self-sufficiency of the woodworking factory with decreased amounts of emissions, savings on the fuel and a better water treatment system.


Boiler plant is planned to be commissioned during the Autumn 2020.