Oversized parts of the main equipment set for biomass fired hot water District Heating plant of 14.8MW capacity in total have reached its destination in Spain! Installation phase will follow and is scheduled to be started shortly after the holidays, in the beginning of the next year.
Moving grate combustion is delivered in two parts + hydraulic fuel feeder with the fuel shutter. Combustion (15MW nominal) is fully prefabricated at the workshop, including refractory.
In addition to the combustion, FERGY AS is supplying for this project: 3-pass hot water boiler (14MW nominal), dry eco (0.8MW nominal), first step flue gas cleaning equipment, fuel handling system as well as ash discharge system, side structures (ducting, servicing platforms), automation and supervision of the installation up to the commissioning.